Marin Transit is in the process of a redevelopment project on Kerner Boulevard in San Rafael, CA. In 2022 we opened a vehicle maintenance facility for our demand-response fleet. Currently, we are working on an adjacent project which will eventually be combined into an integrated parking, maintenance, and electric vehicle charging facility for our demand response fleet.
The ongoing project at 3010 & 3020 Kerner will demolish the existing office structures and make minor improvements to the site, including installation of a solar panel canopy, electric vehicle charging infrastructure, paving, parking lot striping, perimeter fencing, an electronic gate, and lighting improvements for security.
- Phase 1: Demolition of existing buildings (completed)
- Phase 2: Construction of parking facility and charging infrastructure (in progress)
Follow progress with our monthly newsletter below!
Project Documents

Construction Notice
Marin Transit will conduct pile driving at 3010 Kerner Blvd that will cause potential noise and vibrations. Anticipated times for Pile Driving will be between 9am - 3pm on three weekdays.
- *9/8/25 - approx. 30-60 minutes of pile driving - Completed
- 9/15/25 - 9/16/25 - 9am - 3pm potential pile driving
Current Schedule
March 2025
- Construction begins & site set-up/surveying Completed
- Tree & Curb removal (private right of way) Completed
June 2025
- Storm drain and catch basin construction Completed
- Sidewalk and driveway construction (public right of way) Completed
- Installing underground conduit Completed
July 2025
- Continue Installing underground conduit Completed
- Light construction & installation In Progress
- Parking Lot Foundation installation Completed
August 2025
- Continue Light construction & installation In Progress
- Parking lot construction In Progress
- Landscaping & Irrigation In Progress
September 2025
- Solar canopy construction begins In Progress
- Structural steel installation In progress
- Pave Parking lot
- Sidewalk and driveway construction (public right of way)
October 2025
- Install gates/fencing
- Continued landscaping
- Striping
- Continued solar canopy construction
- Install EV Charger
- Energy storage installation & electrical work
- Switchgear for parking lot arrival and installation
November 2025
- PG&E energization of parking lot
February 2026
- Delivery and installation of Switchgear for building at 3000 Kerner
March 2026
- PG&E tie in to 3000 Kerner
- Project completion.